Ramon Airport
Ramon Airport
Israel, Eilat
Airports
Completed
Ramon Airport
Israel, Eilat
Airports
Completed
Ashtrom Industries, through its subsidiaries Israbeton and BG Bond, has provided a variety of building, bonding and coating materials as part of the construction works at Ramon Airport.
57,000cu.m.
of Concrete
5,678
Bonding and coating materials
3.6km.
Length of flight runways


Building, Bonding and Coating Materials for National Infrastructures Project
Works at the Ramon airport included the laying of take-off and landing runways with a length of about 3.6 km. and a parking apron for all types of aircraft.
As part of the construction works, Israbeton Ltd. manufactured 57,000 cu.m. of different types of concrete as well as cement plaster, white plaster and limestone plaster. The building materials were recycled, enabling protection of the environment and keeping the amount of polluting leftovers as low as possible. BG Bond Ltd. supplied 6,000 different materials such as bonding products, acrylic adhesives, paints and decorative coatings, as part of the cladding, waterproofing and concrete renewal operations.